Rapid Charging without waiting for a Grid Upgrade

3 days ago
2 min read

You've found the site. You've chosen the chargers. Your drivers are ready to go electric.


Then the DNO quote lands. A six-figure substation upgrade, with a connection date two or three years away.


This is where most Rapid Charging projects stall. It doesn't have to be.


Why Rapid Chargers are hard on the grid


A single 150 kW DC charger draws more than many small factories. Put four on one site and you need 600 kW available the moment every bay is in use.


Most of the time, they won't all be busy. But the grid connection has to be sized for the worst case. So the DNO looks at the peak, not the average, and that's what triggers the upgrade.


The result is a connection sized for a few busy minutes, paid for every day.


How a battery changes the maths


Battery-buffered charging splits the job in two.


The Battery charges slowly and steadily from your existing supply, often during quiet periods or overnight. When a vehicle plugs in, the Battery delivers the high power the Charger needs. The grid only ever sees a flat, modest draw.


Your site gets Rapid Charging. Your connection stays the same size.


What this looks like in practice


The PowerBase EV Mini, delivered through our ep Pixii partnership, is a good example. It holds 450kWh of lithium iron phosphate (LFP) Storage and can release up to 224kW into connected DC Charging.


It's compact, so it fits sites where space is as tight as capacity. Think depots, car parks, retail sites and fleet yards.


LFP chemistry matters here too. It's thermally stable and handles daily cycling well, which suits a battery that charges and discharges every working day.


Sizing it properly


Getting the battery right depends on how the site is used. The questions we ask first:


  • How many vehicles charge each day, and when?

  • How long do they stay plugged in?

  • How much power does the existing supply have spare, and at what times?

  • How quickly does the battery need to recover between busy periods?


A fleet depot with overnight dwell needs something very different from a public site with back-to-back visits. Undersize the Battery and drivers wait. Oversize it and you've spent money you didn't need to.


More than a workaround


Once the Battery is in, it keeps working when no one is charging. It can shave the site's other peaks and store surplus Solar PV. Some sites can also earn from grid flexibility services. Our piece on Battery Energy Storage Systems covers those benefits.


And if a grid upgrade does arrive later, the Battery doesn't become redundant. It gives you headroom to add more Chargers without a new application.


Stuck in the DNO queue?


If you've had a refusal or an unworkable quote, start with You've been told you can't get more power from the grid. Now what?


Then send us your site details and charging plans. We'll tell you straight whether Battery-buffered DC Charging can get you moving. Get in touch.

 
 
 